project status    
block - a
Block - A Construction Completed
Block - A Image Gallery
     
     
     
     
     
project status    
block - b
Updated on November 2011
Completed Activities as on 30.11.2011
  10 Roof Slabs Completed
  Brick Masonry Works (130 Units Out of 130 Units)
  Internal Plastering Works 130 Units Out of 130 Units)
  Main Door Frame Fixing (130 Units Out of 130 Units)
  Inner Door Frame Fixing (130 Units Out of 130 Units)
  Electrical conduit work (130 units out of 130 units)
On Progress Activities
  Fenesta Fixing work 6,7 & 8th floor in progress (140 nos fixed )
  Lift Testing work at East side is on progress (will be ready in two weeks)
  Water Proofing Works (297 toilets Out of 334 toilets)
  Grano Flooring Works (7 floors Out of 9 floors)
  Tile Works (270 toilets Out of 334 toilets) and 2’x2’ Flooring (53units )
  Internal Plastering Works in Lobby & Staircase 90% completed
  Lift - Internal Plastering 90% completed
  External Plastering Works80 % completed
  Ceiling pop work at the common area (6&half floors out of 9 floors)and 105 units
  Plumbing work (330 toilets out of 334 toilets and 120 kitchen out of 130 kitchen)
  Plumbing duct work (35 nos out of 53 nos)
  Wall putty work (120 units out of 130 units)
Block - B Image Gallery