Completed Activities as on 30.11.2011
 10 Roof Slabs Completed
 Brick Masonry Works (130 Units Out of 130 Units)
 Internal Plastering Works 130 Units Out of 130 Units)
 Main Door Frame Fixing (130 Units Out of 130 Units)
 Inner Door Frame Fixing (130 Units Out of 130 Units)
 Electrical conduit work (130 units out of 130 units)
On Progress Activities
 Fenesta Fixing work 6,7 & 8th floor in progress (140 nos fixed )
 Lift Testing work at East side is on progress (will be ready in two weeks)
 Water Proofing Works (297 toilets Out of 334 toilets)
 Grano Flooring Works (7 floors Out of 9 floors)
 Tile Works (270 toilets Out of 334 toilets) and 2’x2’ Flooring (53units )
 Internal Plastering Works in Lobby & Staircase 90% completed
 Lift - Internal Plastering 90% completed
 External Plastering Works80 % completed
 Ceiling pop work at the common area (6&half floors out of 9 floors)and 105 units
 Plumbing work (330 toilets out of 334 toilets and 120 kitchen out of 130 kitchen)
 Plumbing duct work (35 nos out of 53 nos)
 Wall putty work (120 units out of 130 units)
|